Rule Change RC_2019_03

Type: Standard Rule Change Process

Submitter: Economic Regulation Authority

Title: Method used for the assignment of Certified Reserve Capacity to Intermittent Generators

Market Rules Affected: 4.9.5, 4.10.2, 4.10.3, 4.10.3A, 4.11.1, 4.11.2, 4.11.3C, 4.11.3E, 4.28C.1, 10.5.1, Appendix 9 and the Glossary.

Date Submitted: 17 December 2020

Current Status: The date for publishing the Draft Rule Change Report has been extended in accordance with the Extension Notice published on 12 April 2021. The Draft Rule Change Report is due to be published on 20 April 2021.

Event Date Comments
Notification Published 18/12/2020

First Submission Period 18/12/2020 – 11/02/2021

The submission period is at least 30 B-Days from the publication of the Rule Change Notice.

Draft Rule Change Report Published 20/04/2021
The timeframe for publishing the Draft Rule Change Report was extended in accordance with the Extension Notice published on 12 April 2021.
Second Submission Period 20/04/2021 – 19/05/2021
The submission period is at least 20 B-Days from the publication of the Draft Rule Change Report.
Final Rule Change Report Published 17/06/2021
The Final Rule Change Report must be published within 20 B-Days after the end of the second submission period.
Commencement TBA

Documents related to this Rule Change Proposal

Rule Change Notice and Proposal [421 kB]

Extension Notice (20 January 2021) [97 kB]

Extension Notice (2 March 2021) [87 kB]

Extension Notice (12 April 2021) [86 kb]

Submissions received during first submission period

AEMO [451 kB]

Alinta [179 kB]

Collgar Wind Farm [127 kB]

Synergy [151 kB]

Submissions received out of session

Australian Energy Council [183 kB]

Page last updated: 12 Apr 2021