Type: Standard Rule Change Process
Submitter: Perth Energy
Title: MAC Membership Review
Market Rules Affected: 2.3.5
Date Submitted: 18 May 2010
Current Status: The Amending Rules commenced at 8:00am on 1 November 2010
Event |
Date |
Comments |
Notification Published |
25/05/2010 |
|
First Submission Period |
26/05/2010 - 07/07/2010 |
The submission period is 30 B-Days from the date the IMO published the Draft Report |
Draft Report Published |
03/08/2010 |
Must be published within 20 B-Days of the end of the first submission period |
Second Submission Period |
31/08/2010 |
The submission period is at least 20 B-Days from the date the IMO published the Draft Report |
Final Report Published |
28/09/2010 |
Must be published within 20 B-Days after the end of the second submission period |
Ministerial Approval by |
26/10/2010 |
The Minister approved this Rule Change on 18 October 2010. |
Commencement |
01/11/2010 |
|
Documents related to this change proposal
Submissions received in the first submission period
Submissions received in the second submission period