Type: Standard Rule Change Process
Submitter: Australian Energy Market Operator (AEMO)
Title: Administrative Improvements to Settlement
Market Rules Affected: 6.15.4, 9.2.1, 9.16.2, 9.16.3, 9.16.3A, 9.16.4, 9.17.3, 9.18.1, 9.18.2, 9.18.3, 9.18.4, 9.19.1, 9.19.1A, 9.19.1B (new), 9.19.3, 9.19.5, 9.19.6, 9.19.7, 9.20.3, 9.20.4, 9.20.4A (new), 9.20.5, 9.20.6, 9.20.7, 9.20.7A (new), 9.20.7B (new), 9.20.8, 9.21.1, 9.22.2, 9.22.4, 9.22.6, 9.22.7, 9.22.8, 9.23.1, 9.23.4, 9.23.5, 9.23.6, 9.23.7, 9.24.1, 9.24.2, 9.24.4, 9.24.5, 9.24.6, 9.24.7, 9.24.8, 9.24.8A, 9.24.9, 9.24.10 and the Glossary.
Date Submitted: 18 November 2019
Current Status: The Minister approved the Amending Rules on 17 June 2020. The Amending Rules commenced at 8:00 AM on 2 July 2020.
Notification Published |
27/11/2019
|
|
First Submission Period |
28/11/2019 - 31/01/2020
|
The timeframe for the close of the First Submission period was extended beyond the usual 30 B-Days in accordance with the Rule Change Notice.
|
Draft Rule Change Report Published |
20/03/2020
|
The timeframe for publishing the Draft Rule Change Report was extended in accordance with the Extension Notices published on 28 February 2020 and 13 March 2020.
|
Second Submission Period |
20/03/2020 - 21/04/2020 |
The submission period is at least 20 B-Days from the publication of the Draft Rule Change Report.
|
Final Rule Change Report Published |
20/05/2020
|
The Final Rule Change Report must be published within 20 B-Days after the end of the second submission period.
|
Ministerial Approval
|
17/06/2020
|
The Minister requires 20 B-Days to review the Final Rule Change Report and advise the Rule Change Panel of a decision.
|
Commencement |
02/07/2020
|
The Amending Rules’ commencement was extended in accordance with the Extension Notice published on 18 June 2020.
|
Documents related to this Rule Change Proposal
Rule Change Notice and Proposal [374 kB]
Extension Notice (28 February 2020) [102 kB]
Extension Notice (13 March 2020) [100 kB]
Draft Rule Change Report [613 kB]
Addendum to Draft Rule Change Report [93 kB]
Final Rule Change Report [384 kB]
Extension Notice (18 June 2020) [86 kB]
Commencement Notice (2 July 2020) [140 kB]
Submissions received in the first submission period
Synergy [123 kB]
Western Power [84 kB]
Submissions received in the second submission period
AEMO [715 kB]