Rule Change RC_2018_07

Type: Standard Rule Change Process

Submitter: Public Utilities Office

Title: Removal of constrained off compensation for Outages of network equipment

Market Rules Affected: 7.7.3A, 7.7.6, 7.7.7B (new), 7.7.11 (new), and Chapter 11 (Glossary)

Date Submitted: 14 December 2018

Current Status: The First Submission Period is open until 8 February 2019.

Event Date Comments
Notification Published 17/12/2018
First Submission Period 17/12/2018 - 08/02/2019

The timeframe for the close of the First Submission period was extended beyond the usual 30 B-Days in accordance with the Rule Change Notice.

Draft Rule Change Report Published 11/03/2019 The Draft Rule Change Report must be published within 20 B-Days after the end of the first submission period.
Second Submission Period 11/03/2019 - 08/04/2019 The submission period is at least 20 B-Days from the publication of the Draft Report.
Final Rule Change Report Published 09/05/2019 The Final Rule Change Report must be published within 20 B-Days after the end of the second submission period.
Commencement TBA
 

Documents related to this Rule Change Proposal

Constrained Payments Workshop 24 October 2018 - Minutes [260 kB]

Constrained Payments Workshop 24 October 2018 - Slides [473 kB]

Rule Change Notice and Proposal [421kB]