Skip to content

Rule Change: RC_2017_07

Type: Fast Track Rule Change Process

Submitter: AEMO

Title: Reserve Capacity Mechanism - Transitional Rules

Market Rules Affected: New section 1.24 and the Glossary

Date Submitted: 17 July 2017

Current Status: The Amending Rules commenced on 1 September 2017.

Timeline:

Event Date Comments
Notification Published 26/07/2017
Requests to be Consulted 26/07/2017 - 02/08/2017 The last date a Rule Participant can contact the Rule Change Panel requesting to be consulted on the change
Consultation Period 26/07/2017 – 16/08/2017 Must be completed within 15 B-Days from the publication of the Rule Change Notice
Final Rule Change Report 23/08/2017 The Final Rule Change Report must be published within 20 B-Days after the Rule Change Notice is published
Commencement 01/09/2017

Documents related to this Rule Change Proposal

Rule Change Notice and Proposal [505kB PDF]

Final Rule Change Report [535 kB PDF]

Commencement Notice [129 kB PDF]

Page last updated: 06 Nov 2018