Rule Change: RC_2015_03

Type: Standard Rule Change Proposal

Submitter: IMO

Title: Formalisation of the Process for Maintenance Applications

Market Rules Affected: Clauses 2.24.1, 4.26.2C, 4.26.2CA, 4.26.2CB (new), 4.26.2CC (new), 4.26.2CD (new), 4.28.8, 4.28.9A (new), 4.28.9B (new), 4.28.9C (new), 4.28.9D (new), 4.28.9E (new), the Glossary and Appendix 5A.

Date Submitted: 27 March 2015

Current Status: The timeframe for preparing the Draft Rule Change Report has been further extended in accordance with the Extension Notice published on 20 December 2018. The Draft Rule Change Report is due to be published on 1 April 2019.

Event Date Comments
Notification Published 27/03/2015
First Submission Period 30/03/2015 - 13/05/2015 The submission period is at least 30 B-Days from the date the IMO published the Rule Change Notice.
Further Submission Period 24/10/2018 – 13/11/2018 A call for further submissions was published on 23 October 2018.
Draft Report Published 01/04/2019 The timeframe for publishing the Draft Rule Change Report was further extended in accordance with the Extension Notice published on 20 December 2018.
Second Submission Period 01/04/2019 - 02/05/2019 The submission period is at least 20 B-Days from the date the Rule Change Panel published the Draft Rule Change Report.
Final Report Published 30/05/2019 Must be published within 20 B-Days after the end of the second submission period.
Ministerial Approval 28/06/2019 The Minister requires at least 20 B-Days to review the Final Rule Change Report and advise the Rule Change Panel of a decision.
Commencement TBA

Documents relating to this rule change proposal

Rule Change Notice and Proposal  [313kB]

Extension Notice (21 May 2015) [89kB]

Extension Notice (15 July 2015) [91kB]

Extension Notice (21 August 2015) [89kB]

Extension Notice (18 December 2015) [89kB]

Extension Notice (27 June 2016) [89kB]

Extension Notice (10 April 2017) [135kB]

Extension Notice (21 December 2017) [148kB]

Call for Further Submissions (23 October 2018) [434kB]

Extension Notice (20 December 2018) [153kB]

Submissions received during first submission period

Community Electricity [21kB]

EnerNOC [183kB]

Perth Energy [196kB]

Submissions received during the further submission period

AEMO [154kB]

Alinta Energy [116kB]

Simcoa [147kB]