Rule Change: RC_2015_03

Type: Standard Rule Change Proposal

Submitter: IMO

Title: Formalisation of the Process for Maintenance Applications

Market Rules Affected: Clauses 2.24.1, 4.26.2C, 4.26.2CA, 4.26.2CB (new), 4.26.2CC (new), 4.26.2CD (new), 4.28.8, 4.28.9A (new), 4.28.9B (new), 4.28.9C (new), 4.28.9D (new), 4.28.9E (new), the Glossary and Appendix 5A.

Date Submitted: 27 March 2015

Current Status: The Draft Rule Change Report is due to be published on 31 December 2018. 

Event Date Comments
Notification Published 27/03/2015
First Submission Period 30/03/2015 - 13/05/2015 The submission period is at least 30 B-Days from the date the IMO published the Rule Change Notice.
Further Submission Period 24/10/2018 – 13/11/2018 A call for further submissions was published on 23 October 2018.
Draft Report Published 31/12/2018 The timeframe for publishing the Draft Rule Change Report was further extended in accordance with the Extension Notice published on 21 December 2017.
Second Submission Period 31/12/2018 - 30/01/2019 The submission period is at least 20 B-Days from the date the Rule Change Panel published the Draft Rule Change Report.
Final Report Published 27/02/2019 Must be published within 20 B-Days after the end of the second submission period.
Ministerial Approval 28/03/2019 The Minister requires at least 20 B-Days to review the Final Rule Change Report and advise the Rule Change Panel of a decision.
Commencement TBA
The Commencement date is provisional.

Documents relating to this rule change proposal

Rule Change Notice and Proposal  [313kB]

Extension Notice (21 May 2015) [89kB]

Extension Notice (15 July 2015) [91kB]

Extension Notice (21 August 2015) [89kB]

Extension Notice (18 December 2015) [89kB]

Extension Notice (27 June 2016) [89kB]

Extension Notice (10 April 2017) [135kB]

Extension Notice (21 December 2017) [148kB]

Call for Further Submissions (23 October 2018) [434kB]

Submissions received during first submission period

Community Electricity [21kB]

EnerNOC [183kB]

Perth Energy [196kB]

Submissions received during the further submission period

AEMO [154kB]

Alinta Energy [116kB]

Simcoa [147kB]

Page last updated: 15 Nov 2018