Rule Change: RC_2015_01

Type: Standard Rule Change Proposal

Submitter: IMO

Title: Removal of Market Operation Market Procedures

Market Rules Affected: Clauses 4.28A.3, 7A.1.6, 7A.3.3, 7A.3.19, 7A.3.19A (new), 7A.3.20, 7A.3.21, 7B.3.3, 8.6.2, 9.2.1, 9.4.3, heading 9.2, the Glossary and the Table of Contents.

Date Submitted: 3 March 2015

Current Status: The Draft Rule Change Report is due to be published on 31 December 2018.

Event Date Comments
Notification Published 03/03/2015
First Submission Period 04/03/2015 - 16/04/2015 The submission period is at least 30 B-Days from the date the IMO published the Rule Change Notice.
Further Submission Period  23/10/2018 – 09/11/2018  A call for further submissions was published on 22 October 2018. 
Draft Report Published 31/12/2018 The timeframe for publishing the Draft Rule Change Report was further extended in accordance with the Extension Notice published on 21 December 2017.
Second Submission Period 31/12/2018 – 30/01/2018 The submission period is at least 20 B-Days from the date the Rule Change Panel published the Draft Rule Change Report.
Final Report Published 27/02/2018 Must be published within 20 B-Days after the end of the second submission period.
Commencement TBA
The Commencement date is provisional.

Documents related to this Rule Change Proposal

Rule Change Notice and Proposal [245kB]

Extension Notice (15 May 2015) [87kB]

Extension Notice (22 May 2015) [88kB]

Extension Notice (12 June 2015) [83kB]

Extension Notice (18 December 2015) [88kB]

Extension Notice (27 June 2016) [88kB]

Extension Notice (10 April 2017) [135kB]

Extension Notice (21 December 2017) [147kB]

Call for Further Submissions (22 October 2018) [306kB]

Submissions received during first submission period

Community Electricity [20kB]

Perth Energy [207kB]

Submissions received during further submission period

AEMO [137kB]