Rule Change: RC_2013_05

Type: Standard Rule Change Proposal

Submitter: IMO

Title: LoadWatch, EOI and RDQ Provision

Market Rules Affected: Clauses 3.23, 7A.3.7, 7A.3.7A and the Glossary

Date Submitted: 09 April 2013

Current Status: The Amending Rules commenced on 2 September 2013

Event Date Comments
Notification Published 09/04/2013  
First Submission Period 10/04/2013 - 21/05/2013
The submission period is 30 B-Days from the date the IMO published the Rule Change Notice
Draft Report Published 19/06/2013 Must be published within 20 B-Days of the end of the first submission period
Second Submission Period 20/06/2013 - 17/07/2013 
The submission period is at least  20 B-Days from the date the IMO published the Draft Report
Final Report Published 14/08/2013 
Must be published within 20 B-Days after the end of the second submission period
Commencement 02/09/2013

Documents related to this Rule Change Proposal

Submissions received in the first submission period

Perth Energy [26kB]

Out of Session Submissions received in the first submission period

Submissions received in the second submission period

Page last updated: 06 Nov 2018