Rule Change: RC_2013_03

Type: Fast Track Rule Change Process

Submitter: IMO

Title: LFAS Facility Definition

Market Rules Affected: Clauses 7B.1.6, 7B.2.10 and the Glossary

Date Submitted: 10 April 2013

Current Status: The Amending Rules commenced on 1 June 2013

Event Date Comments
Notification Published 10/04/2013  
Requests to be Consulted 17/04/2013 The last date a Rule Participant can contact the IMO requesting to be consulted on the change.
Consultation Period 11/04/2013 - 02/05/2013
Must be completed within 15 B-Days from the date the notification is published.
Final Rule Change Report Published 09/05/2013 
Must be published within 20 B-Days from the date the notification is published.
Commencement 01/06/2013

Documents related to this Rule Change Proposal

Submissions received during the consultation period

Perth Energy [150kB]

Verve Energy [57kB]