Rule Change: RC_2012_24

Type: Standard Rule Change Process

Submitter: IMO

Title: Cure Notices and Credit Support

Market Rules Affected: Clause 9.23.4

Date Submitted: 18 December 2012

Current Status: The Amending Rules commenced on 1 June 2013

Event Date Comment
Notification Published 18/12/2012  
First Submission Period 19/12/2012 - 4/02/2013
The submission period is 30 B-Days from the date the IMO published the Rule Change Notice
Draft Report Published 05/03/2013
Must be published within 20 B-Days of the end of the first submission period.
Second Submission Period 06/03/2013 - 04/04/2013
The submission period is at least  20 B-Days from the date the IMO publishes the Draft Rule Change Report.
Final Report Published 03/05/2013
Must be published within 20 B-Days after the end of the second submission period.
Commencement 01/06/2013  

Documents related to this Rule Change Proposal

Submissions received in the first submission period

Alinta Energy [31kB]

Synergy [13kB]

Verve Energy [50kB]

Out of session submissions received in the first submission period

Perth Energy [147kB]

Submissions received in the second submission period

Page last updated: 07 May 2017