Rule Change: RC_2012_11

Type: Standard Rule Change Process

Submitter: IMO

Title: Transparency of Outage Information

Market Rules Affected: Clauses 3.18.6, 10.5.1 and the Glossary, and new clauses 7.13.1D, 7.13.1E, 7.13.1F, 7.13.1G.

Date Submitted: 30 July 2012

Date First Published on the IMO Website: 30 July 2012

Current Status: The Amending Rules commenced on 1 October 2013.

Event Date Comments
Notification Published 30/07/2012  
First Submission Period 31/07/2012 - 10/09/2012
The submission period is 30 B-Days from the date the IMO published the Rule Change Notice
Draft Report Published 09/10/2012
Must be published within 20 B-Days of the end of the first submission period
Second Submission Published 10/10/2012 - 06/11/2012
The submission period is at least  20 B-Days from the date the IMO published the Draft Report
Final Report Published 16/04/2013
The timeframe for publishing the Final Rule Change Report has been extended in accordance with the Extension Notice published on 21 March 2013.
Commencement 01/10/2013

Documents related to this Rule Change Proposal

Submissions received in the first submission period

Perth Energy [42kB]

Synergy [19kB]

Verve Energy [34kB]

Submissions received out of session

Alinta [170kB]

Submissions received in the second submission period

Synergy [24kB]

Verve Energy [105kB]

Out of Session submissions received

System Management has advised the IMO that the last sentence on page 4, paragraph 7 is not to be included in the submission.

"That would involve additional costs of approx $250k per annum.  Initially these roles would have low utilisation but that could be expected to tail off over time.  These costs are in addition to those presented in section 3 of this submission."