Rule Change: RC_2012_09

Type: Standard Rule Change Process

Submitter: System Management

Title: Clarification and Calculation of Availability Curve

Market Rules Affected: Clause 4.5.10(e), 4.5.12, 4.5.13

Date Submitted: 27 July 2012

Current Status: The Amending Rules commenced on 1 November 2013

Event Date Comments
Notification Published 27/07/2012  
First Submission Period 30/07/2012 - 07/09/2012
The submission period is 30 B-Days from the date the IMO published the Rule Change Notice.
Draft Report Published 08/10/2012
Must be published within 20 B-Days of the end of the first submission period.
Second Submission Published 09/10/2012 - 05/11/2012
The submission period is at least  20 B-Days from the date the IMO published the Draft Report.
Final Report Published 03/12/2012
Must be published within 20 B-Days after the end of the second submission period.
Ministerial Approval by 18/09/2013 The Final Rule Change Report was approved by the Minister on the 17 September 2013.
Commencement 01/11/2013

Documents related to this Rule Change Proposal

Submissions received in the first submission period

Perth Energy [43kB]

Synergy [20kB]

Verve Energy [136kB]

Submissions received in the second submission period