Rule Change: RC_2010_24

Type: Standard Rule Change Proposal

Submitter: Alinta

Title: Adjustment of Relevant Level for Intermittent Generation Capacity

Market Rules Affected: Clauses 4.11.3A, 7.13.1C (new), 7.7.5B and 7.7.5E (new)

Date Submitted: 03 August 2010

Date First Published on the IMO Website: 09 August 2010

Current Status: The Amending Rules commenced on 1 July 2011

Event Date Comments
Notification Published 09/08/2010  
First Submission Period 10/08/2010 - 20/09/2010 The submission period is 30 B-Days from the date the IMO published the Draft Report
Draft Report Published 18/10/2010 Must be published within 20 B-Days of the end of the first submission period
Second Submission Period 19/10/2010 - 20/01/2010 The submission period has been extended. An extension notice was published on 18 October 2010.
Final Report Published 01/04/2011 The timeframe for preparing the Final Rule Change Report was extended in accordance with the extension notice published 18 October 2010.
Commencement 01/07/2011 Please note that this date is provisional and may be subject to change in the Final Rule Change Report  

Documents related to this change proposal

Submissions received in the first submission period

Perth Energy [32kB]

Verve Energy [27kB]

Submissions received in the second submission period