Skip to content

Rule Change: RC_2010_19

Type: Standard Rule Change Process

Submitter: IMO

Title: Settlement Cycle Timeline

Market Rules Affected: 9.16.3 and new clause 9.16.3A

Date Submitted: 25 October 2010

Current Status: The Amending Rules commenced on 1 May 2011

Event Date Comments
Notification Published 25/10/2010  
First Submission Period 26/10/2010 - 06/12/2010 The submission period is 30 B-Days from the date the IMO published the Draft Report
Draft Report Published 24/01/2011 The timeframe for the Draft Report was extended in accordance with the Extension Notice published on 25 October 2010.
Second Submission Period 25/01/2011 - 22/02/2011 The submission period is at least  20 B-Days from the date the IMO published the Draft Report
Final Report Published 23/03/2011 Must be published within 20 B-Days after the end of the second submission period
Ministerial Approval by 20/04/2011 The Minister approved the Final Report on 6 April 2011.  
Commencement 01/05/2011  

Documents related to this change proposal

Submissions received in the first submission period

Perth Energy [33kB]

Synergy [65kB]

Submissions received in the second submission period

Page last updated: 07 May 2017