Skip to content

Rule Change: RC_2010_14

Type: Standard Rule Change Process

Submitter: IMO

Title: Certification of Reserve Capacity

Market Rules Affected: Clauses 4.1.8, 4.1.9, 4.1.10, 4.1.11, 4.1.12, 4.1.13, 4.1.14, 4.1.16, 4.1.17, 4.1.18, 4.1.20, 4.1.21, (new) 4.1.21A, 4.2.7, 4.4.1, 4.9.3, 4.9.5, 4.9.9, (new) 4.9.9A, 4.10.1, 4.10.2, 4.10.3. (new) 4.10.4, 4.11.1, 4.11.2, 4.11.3A, 4.11.5, (new) 4.11.10, 4.15.1, 4.20.1, 4.20.5A, 4.27.10, 4.27.11A, 4.28C.1, 4.28C.2, 10.5.1 and the Glossary. Changes to 4.13.10, 4.13.13 and 4.26.1 will come into effect if RC_2010_12 and this Rule Change Proposal are both accepted

Date Submitted: 06 December 2010

Current Status: The final set of Amending Rules commenced on 1 January 2012.

Timeline

Event Date Comments
Notification Published 06/12/2010  
First Submission Period 07/12/2010 - 25/01/2011  The timeframe for the first submission period was extended in accordance with the Extension Notice published on 6 December 2010.
Draft Report Published 11/03/2011  The timeframe for preparing the Draft Report was extended in accordance with the Extension Notice published on 4 March 2011.
Second Submission Period 14/03/2011 - 11/04/2011  The submission period is at least  20 B-Days from the date the IMO published the Draft Report
Final Report Published 12/05/2011  Must be published within 20 B-Days after the end of the second submission period
Ministerial Approval by 01/07/2011  The Minister approved the Final Report on 1 July 2011.  
Commencement 08/07/2011 and 01/01/2012 The commencement date for the Amending Rules was extended in accordance with extension notice published on 1 July 2011. 

Documents related to this change proposal

Submissions received during the first submission period

Alinta [83kB]

Perth Energy [47kB]

Synergy [74kB]

Submissions received during the second submission period

Alinta [90kB]

ERM Power [426kB]

Synergy [69kB]

Out of session submissions received

Perth Energy [39kB]

Page last updated: 07 May 2017