Rule Change: RC_2009_03

Type: Standard Rule Change Process

Submitter: System Management

Title: Provision of Intermittent Generator Forecast Information

Market Rules Affected: Clause 7.2.5

Date Submitted: 16 February 2009

Date First Published on the IMO Website: 18 February 2009

Current Status: The Amending Rules commenced at 8:00am 1 July 2009

Event Date Comments
Notification Published 18/02/2009  
First Submission period 18/02/2009 – 1/04/2009 The submission period is 6 weeks from the date the IMO published the notification
Draft Report published 22/04/2009 Must be published within 20 B-Days after the end of the submission period
Second submission period 23/04/2009 – 21/05/2009 The submission period is 20 B-Days from the date the IMO published the Draft Report
Final Report Published 19/06/2009 Must be published within 20 B-Days after the end of the second submission period
Rule Commencement 01/07/2009  

Documents related to this change proposal

Submissions received in the first submission period

Submissions received in the second submission period

Perth Energy [42kB]

Synergy [48kB]

Page last updated: 07 May 2017