2010 Binningup Desalination Plant Augmentation – Regulatory Test proposal by Western Power

In 2010 the ERA agreed to Western Power’s request to waive the regulatory test for a proposed major augmentation to install a second 330/132 kV transformer at Kemerton Terminal, establish a 132 kV switchyard at Kemerton Terminal, and install approximately 10 km of 132 kV transmission line from Kemerton Terminal to the Binningup desalination plant.

ERA Papers

Showing 1 results.
  
    
Date Documents File type
06-Jan-10 Determination
Adobe PDF 81 kB

Western Power's application

Showing 1 results.
  
    
Date Documents File type
06-Jan-10 Western Power request for waiver of Regulatory Test
Adobe PDF 871 kB