APA Transmission (Roy Hill) holds an electricity integrated regional licence and is authorised to generate, transmit, distribute and supply electricity from the Newman Power Station, which has a reported capacity of 238 megawatts, to the Roy Hill mine site in the Pilbara region.
Alinta Energy Transmission (Roy Hill) was originally granted the licence and it was transferred to APA Transmission (Roy Hill) on 14 June 2024.
| Licensee information |
|---|
| APA Transmission (Roy Hill) Pty Ltd |
| ABN 81 159 279 857 |
| Licence information | Relevant dates |
|---|---|
| Licence granted | 1 October 2013 |
| Licence expires | 30 September 2043 |
| Current audit period | 1 October 2025 to 30 September 2029 |
| Type of customers | Number of customers as at 30 June 2025 |
|---|---|
| Large use business | 2 |
| Total | 2 |