Type: Standard Rule Change Process
Submitter: Public Utilities Office
Title: Full Runway Allocation of Spinning Reserve Costs
Market Rules Affected: Appendix 2
Date Submitted: 26 November 2018
Current Status: The Amending Rules commenced on 1 September 2019.
| Notification Published |
29/11/2018 |
|
| First Submission Period |
29/11/2018 – 30/01/2019 |
The submission period is at least 30 B-Days from the publication of the Rule Change Notice.
|
| Draft Rule Change Report Published |
27/02/2019 |
The Draft Rule Change Report must be published within 20 B-Days after the end of the first submission period. |
| Second Submission Period |
27/02/2019 – 28/03/2019 |
The submission period is at least 20 B-Days from the publication of the Draft Report.
|
| Final Rule Change Report Published |
30/04/2019 |
The Final Rule Change Report must be published within 20 B-Days after the end of the second submission period.
|
| Commencement |
01/09/2019 |
|
Documents related to this Rule Change Proposal
Rule Change Notice and Proposal [458kB]
Draft Rule Change Report [769 kB]
Final Rule Change Report [448kB]
Commencement Notice (1 September 2019) [146kB]
Submissions received in the first submission period
AEMO [125kB]
Australian Energy Council [107kB]
Bluewaters Power [150kB]
Community Electricity [22kB]
Perth Energy [88kB]
Submissions received in the second submission period
AEMO [86kB]
Bluewaters Power [228kB]