Type: Standard Rule Change Process
Submitter: Collgar Wind Farm
Title: Capacity Credit Allocation Methodology for Intermittent Generators
Market Rules Affected: 10.5.1, 11, Appendix 9
Date Submitted: 1 March 2018
Current Status: The date for publishing the Draft Rule Change Report has been further extended in accordance with the Extension Notice published on 2 December 2020. The Draft Rule Change Report is due to be published on 30 June 2021.
Timeline:
| Notification Published |
07/03/2018 |
|
| First Submission Period |
07/03/2018– 20/04/2018 |
The submission period is at least 30 B-Days from the publication of the Rule Change Notice. |
| Draft Rule Change Report Published |
30/06/2021
|
The timeframe for publishing the Draft Rule Change Report was extended in accordance with the Extension Notice published on 2 December 2020.
|
| Second Submission Period |
30/06/2021 - 28/07/2021 |
The submission period is at least 20 B-Days from the publication of the Draft Report.
|
| Final Rule Change Report Published |
25/08/2021
|
The Final Rule Change Report must be published within 20 B-Days after the end of the second submission period.
|
| Commencement |
TBA
|
|
Documents related to this Rule Change Proposal
Rule Change Notice and Proposal [329kB PDF]
Extension Notice (26 April 2018) [151kB PDF]
Extension Notice (18 April 2019) [103kB PDF]
Extension Notice (9 December 2019) [102kB PDF]
Extension Notice (2 December 2020) [103kB PDF]
Submissions received during first submission period
AEMO [270kB PDF]
Community Electricity [22kB PDF]
Noel Schubert [353kB PDF]
Perth Energy [93kB PDF]
PUO [83kB PDF]
Shane Cremin [89kB PDF]
Synergy [113kB PDF]