Type: Standard Rule Change Proposal
Submitter: IMO
Title: Omnibus Rule Change
Market Rules Affected: Clauses 2.12.1, 2.12.2, 2.12.3, 2.12.4, 2.12.5, 2.13.15, 2.13.16, 2.13.21, 2.16.9FA, 2.22.8B, 2.23.1, 2.23.4, 2.23.9, 2.24.6, 2.30A.6, 2.31.23, 2.33.2, 2.33.5, 2.34.14, 2.38.4, 3.2.5 ,3.5.1, 3.11.8A, 3.16.4, 3.16.9, 3.21B.8, 3.22.1, 4.5.1, 4.5.2, 4.7.1, 4.13.11B, 4.27.1, 4.27.2, 4.27.10, 4.27.10A, 4.29.3, 5.1, 5.1.1, 5.1.2, 5.1.3, 5.1.4, 5.2.1, 5.2.2, 5.2.3, 5.2.4, 5.2.5, 5.2.6, 5.2.7, 5.3.1, 5.3.2, 5.3.3, 5.3.4, 5.3.5, 5.3.6, 5.3.7, 5.3.8, 5.3.9, 5.4.1, 5.4.2, 5.4.3, 5.4.4, 5.4.5, 5.4.6, 5.4.7, 5.4.8, 5.4.9, 5.4.10, 5.4.11, 5.4.12, 5.4.13, 5.4.14, 5.5, 5.5.1, 5.5.2, 5.5.3, 5.5.4, 5.6.1, 5.6.2, 5.6.3, 5.8.1, 5.8.2, 5.8.3, 5.8.4, 5.8.5, 5.8.6, 5.8.7, 5.8.8, 6.2.4C, 7.13.1, 8.4.5, 8.6.1, 9.2.1, 9.3.2, 9.4.7, 9.9.3A, 9.12.1, 9.12.2, 9.14.2, 9.20.1, the Glossary and Appendices 1 and 5.
Date Submitted: 22 December 2014
Current Status: The Amending Rules commenced at 8:00 AM on 11 January 2019 and 1 July 2019.
| Notification Published |
22/12/2014 |
|
| First Submission Period |
22/12/2014 – 13/02/2015 |
The submission period has been extended to 35 B-Days from the date the IMO published the Rule Change Notice. |
| Draft Report Published |
16/03/2015 |
Must be published within 20 B-Days of the end of the first submission period. |
| Second Submission Period |
16/03/2015 – 15/04/2015 |
The submission period is at least 20 B-Days from the date the IMO published the Draft Report.
|
| Further Submission Period |
15/10/2018 – 09/11/2018 |
A call for further submissions was published on 12 October 2018. |
| Final Rule Change Report Published |
10/12/2018 |
The timeframe for preparing the Final Rule Change Report was extended in accordance with the Extension Notice published on 21 December 2017.
|
Ministerial Approval
|
08/01/2019
|
|
| Commencement |
11/01/2019
01/07/2019
|
Amendments to clause 2.34.14 commenced on 1 July 2019. The remaining Amending Rules commenced on 11 January 2019.
|
Documents related to this Rule Change Proposal
Rule Change Notice and Proposal [408kB]
Draft Rule Change Report [475kB]
Extension Notice (7 May 2015) [125kB]
Extension Notice (22 May 2015) [141kB]
Extension Notice (12 June 2015) [142kB]
Extension Notice (18 December 2015) [88kB]
Extension Notice (27 June 2016) [88kB]
Extension Notice (10 April 2017) [136 kB]
Extension Notice (21 December 2017) [149 kB]
Call for Further Submissions (12 October 2018) [667 kB]
Final Rule Change Report [927 kB]
Commencement Notice (11 January 2019) [202 kB]
Commencement Notice (1 July 2019) [80 kB PDF]
Submissions received in the first submission period
Community Electricity [20kB]
Perth Energy [196kB]
Submissions received in the further submission period
AEMO [48 kB]