Type: Standard Rule Change Process
Submitter: IMO
Title: Delay of Resource Plan Submissions
Market Rules Affected: 6.5.1 (a) and 6.5A.1(a)
Date Submitted: 10 April 2008
Date First Published on the IMO Website: 11 April 2008
Date Final Report Published: 18 August 2008
Current Status: Closed. The Amending Rules resulting from this Rule Change commenced at 08.00am on 20 August 2008
Preliminary Timeline for this change
Event |
Date |
Comments |
Proposal Received by IMO |
10/04/2008 |
|
Notification Published |
11/04/2008 |
|
First Submission period |
11/04/2008 – 23/05/2008 |
The submission period is 6 weeks from the date the IMO published the notification |
Draft Report published |
23/06/2008 |
Must be published within 20 B-Days after the end of the submission period |
Second submission period |
24/06/2008 – 21/07/2008 |
The submission period is 20 B-Days from the date the IMO published the Draft Report |
Final Report Published |
18/08/2008 |
Must be published within 20 B-Days after the end of the second submission period |
Rule Commencement |
20/08/2008 |
|
Documents related to this change proposal
Submissions received in the first submission period