Type: Standard Rule Change Process
Submitter: IMO
Title: Information from Network Operators
Market Rules Affected: 4.11.5 and 10.2.2
Date Submitted: 10 June 2008
Date First Published on the IMO Website: 13 June 2008
Date Final Report Published: 20 October 2008
Current Status: Closed for public submissions. Procedure Change Report being prepared. Publication date TBA
| Event |
Date |
Comments |
| Proposal Received by IMO |
10/06/2008 |
|
| Notification Published |
13/06/2008 |
|
| First Submission period |
13/06/2008 – 25/07/2008 |
The submission period is 6 weeks from the date the IMO published the notification |
| Draft Report published |
22/08/2008 |
Must be published within 20 B-Days after the end of the submission period |
| Second submission period |
25/08/2008 – 19/09/2008 |
The submission period is 20 B-Days from the date the IMO published the Draft Report |
| Final Report Published |
20/10/2008 |
Must be published within 20 B-Days after the end of the second submission period |
| Rule Commencement |
1/11/2008 |
|
Documents related to this change proposal
Submissions received in the first submission period