Type: Fast Track Rule Change Process
Submitter: Griffin Energy
Title: NTDL new and Overnight Loads
Market Rules Affected: 4.28.9 and Appendix 5 (amended). Appendix 5A (new)
Date Submitted: 20 February 2008
Date First Published on the IMO Website: 29 February 2008
Date Final Report Published: 02 April 2008
Current Status: Closed. The Amending Rules commenced at 08.00am on 1 May 2008
Event |
Date |
Comments |
Proposal Received by IMO |
20/02/2008 |
|
Notification Published |
29/02/2008 |
|
Requests to be Consulted |
10/03/2008 |
The last date a Rule Participant can contact the IMO requesting to be consulted on the change. |
Consultation Period |
04/03/2008 – 26/03/2008 |
Must be completed within 15 B-Days from the date the notification is published |
Final Report Published |
02/04/2008 |
Must be published within 20 B-Days from the date the notification is published |
Rule Commencement |
01/05/2008 |
|
Documents related to this change proposal