Type: Fast Tracked
Submitter: Western Power
Title: Network Control Service Procurement Requirements
Market Rules Affected: 5.2.1, 5.2.2
Date Submitted: 15 October 2007
Date First Published on the IMO Website: 19 November 2007
Date Final Report Published: 19 November 2007
Current Status: Closed. The amendments to Chapter 5 commenced on 1 December 2007
Timeline
Event |
Date |
Comments |
Proposal Received by IMO |
15-10-2007 |
|
Notification Published |
22-10-2007 |
|
Requests to be Consulted |
29-10-2007 |
The last date a Rule Participant can contact the IMO requesting to be consulted on the change. |
Consultation Period |
23-10-2007 – 12-11-2007 |
Must be completed within 15 B-Days from the date the notification is published |
Final Report Published |
19-11-2007 |
Must be published within 20 B-Days from the date the notification is published |
Rule Commencement Date |
01-12-2007 |
|