Submitter: Wesfarmers Premier Power Sales
Title: Reserve Capacity Testing Payments
Market Rules Affected: 4.28.8
Date Submitted: 13 September 2007
Date First Published on the IMO Website: 17 September 2007
Date Final Report Published: 17 January 2008
Current Status: Closed. The amendments to the Market Rules commenced on 1 February 2008
Proposed Timeline for this change
| Event |
Date |
Comments |
| Proposal Received by IMO |
13-09-2007 |
|
| Notification Published |
17-09-2007 |
|
| First Submission period |
17-09-2007 – 29-10-2007 |
The submission period is 6 weeks from the date the IMO published the notification |
| Draft Report published |
26-11-2007 |
Must be published within 20 B-Days after the end of the submission period |
| Second submission period |
26-11-2007 – 24-12-2007 |
The submission period is 20 B-Days from the date the IMO published the Draft Report |
| Final Report Published |
17-01-2008 |
Must be published within 20 B-Days after the end of the second submission period |
| Rule Commencement |
01-02-2008 |
|
Documents related to this change proposal
Submissions received in the first submission period
Submissions received in the second submission period