2010 Binningup Desalination Plant Augmentation – Regulatory Test proposal by Western Power

In 2010 the ERA agreed to Western Power’s request to waive the regulatory test for a proposed major augmentation to install a second 330/132 kV transformer at Kemerton Terminal, establish a 132 kV switchyard at Kemerton Terminal, and install approximately 10 km of 132 kV transmission line from Kemerton Terminal to the Binningup desalination plant.

ERA Papers

Date Documents File type
06-Jan-10 Determination
Adobe PDF 81 kB

Western Power's application

Date Documents File type
06-Jan-10 Western Power request for waiver of Regulatory Test
Adobe PDF 871 kB